Progress update of out of sequence activities

Member for

14 years 11 months

Zoltan,

Thank you, I have added the actual cost manually.

Best Regards,

Sunil

Member for

16 years 3 months

the budgeted units wil be updated if you have Recalcuate actual units and costs whne duration % complete changes. This is in the calculations tab. 

The actual cost have to be updated manually but the units wil be updated 

Member for

16 years 3 months

the budgeted units wil be updated if you have Recalcuate actual units and costs whne duration % complete changes. This is in the calculations tab. 

The actual cost have to be updated manually but the units wil be updated 

Member for

14 years 11 months

Zoltan,

Already updated with actual start and actual finish.

Using percentage complete type - Duration percentage

Regards,

Sunil.

Member for

16 years 3 months

are you putting an actual start and an actual fnish DATES on the activities ?

 

what type of percent complete are you using ?

Member for

14 years 11 months

Dear Experts,

After updating the Baseline , Actual budget cost of  many of the activities  not displaying.( Activities which are having schedule percentage - 0% but activity percentage -100%) . Why it is happening.? Actualy those activities 100% completed during the schedule period.

This is affecting the EV calculations.

Your reply will be highly appreciable.

Beast Regards,

Sunil.