After updating the Baseline , Actual budget cost of many of the activities not displaying.( Activities which are having schedule percentage - 0% but activity percentage -100%) . Why it is happening.? Actualy those activities 100% completed during the schedule period.
Member for
14 years 11 monthsZoltan,Thank you, I have
Zoltan,
Thank you, I have added the actual cost manually.
Best Regards,
Sunil
Member for
16 years 3 monthsthe budgeted units wil be
the budgeted units wil be updated if you have Recalcuate actual units and costs whne duration % complete changes. This is in the calculations tab.
The actual cost have to be updated manually but the units wil be updated
Member for
16 years 3 monthsthe budgeted units wil be
the budgeted units wil be updated if you have Recalcuate actual units and costs whne duration % complete changes. This is in the calculations tab.
The actual cost have to be updated manually but the units wil be updated
Member for
14 years 11 monthsZoltan,Already updated with
Zoltan,
Already updated with actual start and actual finish.
Using percentage complete type - Duration percentage
Regards,
Sunil.
Member for
16 years 3 monthsare you putting an actual
are you putting an actual start and an actual fnish DATES on the activities ?
what type of percent complete are you using ?
Member for
14 years 11 monthsDear Experts,After updating
Dear Experts,
After updating the Baseline , Actual budget cost of many of the activities not displaying.( Activities which are having schedule percentage - 0% but activity percentage -100%) . Why it is happening.? Actualy those activities 100% completed during the schedule period.
This is affecting the EV calculations.
Your reply will be highly appreciable.
Beast Regards,
Sunil.