Hi Yakubu

There are two conditions to maintain this item manually:

1. The activity must be started, as Jerome wrote

2. Percent complete type must be physical. For the two other types (duration, units) it is always calculated by P6.

Regards

Dieter

Member for

21 years 9 months

Hi Yakubu,

You also need to update Actual Start Date for the updated Activity % Complete to be reflected.

 