Planning, Scheduling & Programming Discussion Member for 18 years 9 months Member for 18 years 10 months Submitted by Dieter Wambach on Wed, 2014-08-27 13:47 Permalink Hi Yakubu There are two Hi Yakubu There are two conditions to maintain this item manually: 1. The activity must be started, as Jerome wrote 2. Percent complete type must be physical. For the two other types (duration, units) it is always calculated by P6. Regards Dieter Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Wed, 2014-08-27 13:05 Permalink Hi Yakubu,You also need to Hi Yakubu, You also need to update Actual Start Date for the updated Activity % Complete to be reflected. =jerome Log in or register to post comments
Member for 18 years 9 months Member for 18 years 10 months Submitted by Dieter Wambach on Wed, 2014-08-27 13:47 Permalink Hi Yakubu There are two Hi Yakubu There are two conditions to maintain this item manually: 1. The activity must be started, as Jerome wrote 2. Percent complete type must be physical. For the two other types (duration, units) it is always calculated by P6. Regards Dieter
Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Wed, 2014-08-27 13:05 Permalink Hi Yakubu,You also need to Hi Yakubu, You also need to update Actual Start Date for the updated Activity % Complete to be reflected. =jerome
Member for
18 years 9 monthsHi Yakubu There are two
Hi Yakubu
There are two conditions to maintain this item manually:
1. The activity must be started, as Jerome wrote
2. Percent complete type must be physical. For the two other types (duration, units) it is always calculated by P6.
Regards
Dieter
Member for
21 years 9 monthsHi Yakubu,You also need to
Hi Yakubu,
You also need to update Actual Start Date for the updated Activity % Complete to be reflected.
=jerome