hye...anyone can help me..i need example activity shedulling that high rise building such condominium or apartment in 4 block and duration 3 year...please help me..
Member for
17 years 7 months
Member for17 years7 months
Submitted by Muhammad Zeesh… on Thu, 2014-05-15 13:12
Activity NameOriginal Duration Design and Engineering51 Design Building Addition23 Design43 Review and Approve Designs9 Assemble Technical Data for Heat Pump3 Review Technical Data on Heat Pumps8 Procurement132 Prepare and Solicit Bids for Heat Pump10 Review Bids10 Prepare and Solicit Bids for Flooring5 Review Bids for Heat Pump2 Review Bids for Flooring3 Award Contract for Heat Pump10 Review Bids for Brick3 Award Contract for Flooring1 Award Contract for Brick2 Fabricate and Deliver Flooring58 Deliver Brick58 Fabricate and Deliver Heat Pump and Controls88 Sitework 114 Site work I50 Sitework95 Site work II45 Foundation79 Foundation64 Excavation24 Begin Building Construction0 Excavation10 Form Work12 Install Underground Water Lines5 Install Storm water lines10 Concrete79 Site Preparation10 Form/Pour Concrete Footings10 Concrete Foundation Walls14 Form and Pour Slab10 Backfill and Compact Walls5 Foundation Phase Complete0 Structure 172 Structure143 Erect Structural Frame40 Begin Structural Phase0 Floor Decking28 Concrete First Floor60 Erect Stairwell and Elevator Walls10 Concrete Basement Slab15 Concrete Second Floor15 Mechanical/Electrical Systems133 Rough-In Phase Begins0 Rough In Complete0 Elevator 165 Elevator138 Install Elevator Rails and Equipment40 Install Elevator Cab and Finishes20 Plumbing and Electrical181 Set Mechanical and Electrical Equipment15 Electrical Costs152 Rough-In Plumbing/Piping45 Install Wiring and Cable45 Connect Equipment3 HVAC 186 HVAC, Plumbing & Fire Protection155 Install HVAC Ducts25 Insulate Ducts2 Set Heat Pump5 Relocate HVAC Chiller3 Startup and Test HVAC1 Install AC Grills and Registers5 Test and Balance HVAC Equipment1 Exterior Finishes278 Exterior Finish Costs205 Brick 266 Assemble Brick Samples3 Review and Approve Brick Samples10 Brick Exterior Walls14 Roof 10 Insulation and Built-up Roofing10 Doors and Windows3 Install Door and Window Frames1 Install Exterior Doors and Windows2 Interior Finishes373 Drywall in Offices15 Interior Finish Costs44 Finishes Phase Begins0 Finishes Milestone0 Touch-up and Clean-up1 Building Addition Complete0 Punch List2 Plumbing and Lighting Fixtures17 Install Lighting Fixtures3 Install Plumbing Fixtures2 Floor and Carpeting362 Assemble and Submit Flooring Samples8 Review and Approve Flooring10 Install Floor and Carpeting5 Carpentry30 Install Ceiling Grid15 Finish Carpentry and Millwork5 Paint 36 Paint Building Interior30
Muhammad you are absolutely right this forum is made to help all planners in our community.
People like Gary don’t understand this. Most of the planners who write that sort of comments spend most of their office time on internet and rest of the time doing some design plans for desktop surveys.
If you don’t have any knowledge how do you share something!!! But can give loads of lame excuses.
I hope this example help you. Most people in this forum share their experience because they have knowledge
Activity NameOriginal DurationRemaining DurationStartFinishTotal FloatCity Center Office Building Addition68155401-Nov-10 A3-Jul-130 Design and Engineering107001-Nov-10 A06-Apr-11 A Design Building Addition55001-Nov-10 A19-Jan-11 A Start Office Building Addition Project0001-Nov-10 A Review and Approve Designs22017-Jan-11 A17-Feb-11 A Assemble Technical Data for Heat Pump7016-Feb-11 A25-Feb-11 A Review Technical Data on Heat Pumps27024-Feb-11 A06-Apr-11 A Foundation1469823-Feb-11 A19-Sep-11175 Begin Building Construction0028-Feb-11 A Site Preparation43023-Feb-11 A18-Apr-11 A Excavation24242-May-116-Jun-11127 Install Underground Water Lines12123-Jun-1121-Jun-11127 Install Underground Electric Conduit12123-Jun-1121-Jun-11127 Form/Pour Concrete Footings242421-Jun-1126-Jul-11127 Concrete Foundation Walls242425-Jul-1126-Aug-11127 Form and Pour Slab121226-Aug-1114-Sep-11127 Backfill and Compact Walls5513-Sep-1119-Sep-11127 Foundation Phase Complete00 19-Sep-11178 Structure15115119-Sep-1120-Apr-12306 Erect Structural Frame484819-Sep-1125-Nov-11127 Begin Structural Phase0025-Nov-11 418 Floor Decking343425-Nov-1113-Jan-12127 Concrete First Floor363611-Jan-121-Mar-12127 Erect Stairwell and Elevator Walls24241-Mar-124-Apr-12139 Concrete Basement Slab24241-Mar-124-Apr-12139 Concrete Second Floor36361-Mar-1220-Apr-12127 Structure Complete00 20-Apr-12127 Mechanical/Electrical Systems56254914-Apr-11 A26-Jun-130 Rough-In Phase Begins0012-Mar-12 234 Rough In Complete00 5-Feb-130 Elevator2182184-Apr-1212-Feb-1390 Install Elevator Rails and Equipment334-Apr-126-Apr-12217 Install Elevator Cab and Finishes555-Feb-1312-Feb-1391 HVAC56254914-Apr-11 A26-Jun-130 Prepare and Solicit Bids for Heat Pump15214-Apr-11 A4-May-110 Review Bids for Heat Pump10104-May-1117-May-110 Award Contract for Heat Pump6617-May-1125-May-110 Fabricate and Deliver Heat Pump and Controls42242225-May-1123-Jan-130 Install HVAC Ducts242412-Mar-1213-Apr-12186 Insulate Ducts5518-Jun-1225-Jun-12140 Set Heat Pump12124-Jan-1322-Jan-130 Relocate HVAC Chiller7722-Jan-131-Feb-130 Startup and Test HVAC221-Feb-135-Feb-130 Install AC Grills and Registers558-Apr-1315-Apr-1323 Test and Balance HVAC Equipment2221-Jun-1326-Jun-130 Plumbing and Electrical25825820-Jan-1223-Jan-136 Set Mechanical and Electrical Equipment363620-Jan-1212-Mar-12186 Rough-In Plumbing/Piping3324-Aug-1229-Aug-1272 Install Wiring and Cable363631-Aug-1223-Oct-1272 Connect Equipment1122-Jan-1323-Jan-136 Exterior Finishes33628917-Feb-11 A19-Jun-12266 Close-In Phase Begins0015-May-12 296 Building Enclosed00 18-Jun-12127 Brick31226517-Feb-11 A15-May-12124 Assemble Brick Samples0017-Feb-11 A Review and Approve Brick Samples30028-Feb-11 A13-Apr-11 A Prepare and Solicit Bids for Brick Exterior15018-Mar-11 A13-Apr-11 A Review Bids for Brick15008-Apr-11 A28-Apr-11 A Award Contract for Brick5421-Apr-11 A5-May-11377 Deliver Brick115-May-116-May-11377 Brick Exterior Walls171720-Apr-1215-May-12127 Roof242415-May-1219-Jun-12124 Insulation and Built-up Roofing242415-May-1219-Jun-12127 Doors and Windows7727-Apr-128-May-12152 Install Door and Window Frames3327-Apr-121-May-12156 Install Exterior Doors and Windows551-May-128-May-12156 Interior Finishes60155425-Feb-11 A3-Jul-130 Drywall in Offices36365-Feb-1327-Mar-130 Touch-up and Clean-up2219-Jun-1324-Jun-130 Finishes Complete00 26-Jun-130 Punch List5526-Jun-133-Jul-130 Building Addition Complete00 3-Jul-130 Plumbing and Lighting Fixtures44448-Apr-1310-Jun-137 Install Lighting Fixtures778-Apr-1317-Apr-1321 Install Plumbing Fixtures553-Jun-1310-Jun-137 Floor and Carpeting58153425-Feb-11 A4-Jun-130 Assemble and Submit Flooring Samples0025-Feb-11 A Review and Approve Flooring28025-Feb-11 A11-Apr-11 A Prepare and Solicit Bids for Flooring24504-Apr-11 A6-May-11231 Review Bids for Flooring15156-May-1127-May-11231 Award Contract for Flooring5527-May-116-Jun-11231 Fabricate and Deliver Flooring2792793-Jun-116-Jul-12231 Install Floor and Carpeting121216-May-134-Jun-130 Carpentry595927-Mar-1319-Jun-130 Install Ceiling Grid363627-Mar-1316-May-130 Finish Carpentry and Millwork12123-Jun-1319-Jun-130 Paint121214-Feb-134-Mar-1376 Paint Building Interior121214-Feb-134-Mar-1377
Member for
17 years 7 months
Member for17 years7 months
Submitted by Muhammad Zeesh… on Tue, 2014-05-13 20:38
Gary its a shame that people dont help each other i am not ask for the programme i am just asking for the list of activities
List of activities does not belongs to any programme and it is always good to share your experience and best practices you have used.
Those who not share are mostly P6 jockey and I appreciate and salute all those project professional who are helping planning community without thinking about doesn't know how to do their job to stay in a job which they don't deserve,feel it is giving away their experience for free" they all are mean little buggers and they should not be on this forum
Cheers
Member for
17 years 7 months
Member for17 years7 months
Submitted by Muhammad Zeesh… on Tue, 2014-05-13 19:15
There are high rise building such as Water Tank Tower with a revolving Restaurant on Top, Guard House Tower Building around a perimeter fence of a Military Compound, Tower buildings such as in Dubai.
The list of activities depends on what is required by the Contract Project.
Regards,
Member for
17 years 7 months
Member for17 years7 months
Submitted by Muhammad Zeesh… on Sun, 2014-05-11 15:17
Member for
16 years 3 monthseven easierfoundations1st
even easier
foundations
1st floor
2nd floor repeat copy cut paste
Member for
8 years 6 monthshye...anyone can help me..i
hye...anyone can help me..i need example activity shedulling that high rise building such condominium or apartment in 4 block and duration 3 year...please help me..
Member for
17 years 7 monthsMy gratitude knows no bounds
My gratitude knows no bounds to all those who help me
Member for
15 years 11 monthsActivity NameOriginal
Activity NameOriginal Duration Design and Engineering51 Design Building Addition23 Design43 Review and Approve Designs9 Assemble Technical Data for Heat Pump3 Review Technical Data on Heat Pumps8 Procurement132 Prepare and Solicit Bids for Heat Pump10 Review Bids10 Prepare and Solicit Bids for Flooring5 Review Bids for Heat Pump2 Review Bids for Flooring3 Award Contract for Heat Pump10 Review Bids for Brick3 Award Contract for Flooring1 Award Contract for Brick2 Fabricate and Deliver Flooring58 Deliver Brick58 Fabricate and Deliver Heat Pump and Controls88 Sitework 114 Site work I50 Sitework95 Site work II45 Foundation79 Foundation64 Excavation24 Begin Building Construction0 Excavation10 Form Work12 Install Underground Water Lines5 Install Storm water lines10 Concrete79 Site Preparation10 Form/Pour Concrete Footings10 Concrete Foundation Walls14 Form and Pour Slab10 Backfill and Compact Walls5 Foundation Phase Complete0 Structure 172 Structure143 Erect Structural Frame40 Begin Structural Phase0 Floor Decking28 Concrete First Floor60 Erect Stairwell and Elevator Walls10 Concrete Basement Slab15 Concrete Second Floor15 Mechanical/Electrical Systems133 Rough-In Phase Begins0 Rough In Complete0 Elevator 165 Elevator138 Install Elevator Rails and Equipment40 Install Elevator Cab and Finishes20 Plumbing and Electrical181 Set Mechanical and Electrical Equipment15 Electrical Costs152 Rough-In Plumbing/Piping45 Install Wiring and Cable45 Connect Equipment3 HVAC 186 HVAC, Plumbing & Fire Protection155 Install HVAC Ducts25 Insulate Ducts2 Set Heat Pump5 Relocate HVAC Chiller3 Startup and Test HVAC1 Install AC Grills and Registers5 Test and Balance HVAC Equipment1 Exterior Finishes278 Exterior Finish Costs205 Brick 266 Assemble Brick Samples3 Review and Approve Brick Samples10 Brick Exterior Walls14 Roof 10 Insulation and Built-up Roofing10 Doors and Windows3 Install Door and Window Frames1 Install Exterior Doors and Windows2 Interior Finishes373 Drywall in Offices15 Interior Finish Costs44 Finishes Phase Begins0 Finishes Milestone0 Touch-up and Clean-up1 Building Addition Complete0 Punch List2 Plumbing and Lighting Fixtures17 Install Lighting Fixtures3 Install Plumbing Fixtures2 Floor and Carpeting362 Assemble and Submit Flooring Samples8 Review and Approve Flooring10 Install Floor and Carpeting5 Carpentry30 Install Ceiling Grid15 Finish Carpentry and Millwork5 Paint 36 Paint Building Interior30
Member for
14 years 7 monthsMuhammad you are absolutely
Muhammad you are absolutely right this forum is made to help all planners in our community.
People like Gary don’t understand this. Most of the planners who write that sort of comments spend most of their office time on internet and rest of the time doing some design plans for desktop surveys.
If you don’t have any knowledge how do you share something!!! But can give loads of lame excuses.
I hope this example help you. Most people in this forum share their experience because they have knowledge
Activity NameOriginal DurationRemaining DurationStartFinishTotal FloatCity Center Office Building Addition68155401-Nov-10 A3-Jul-130 Design and Engineering107001-Nov-10 A06-Apr-11 A Design Building Addition55001-Nov-10 A19-Jan-11 A Start Office Building Addition Project0001-Nov-10 A Review and Approve Designs22017-Jan-11 A17-Feb-11 A Assemble Technical Data for Heat Pump7016-Feb-11 A25-Feb-11 A Review Technical Data on Heat Pumps27024-Feb-11 A06-Apr-11 A Foundation1469823-Feb-11 A19-Sep-11175 Begin Building Construction0028-Feb-11 A Site Preparation43023-Feb-11 A18-Apr-11 A Excavation24242-May-116-Jun-11127 Install Underground Water Lines12123-Jun-1121-Jun-11127 Install Underground Electric Conduit12123-Jun-1121-Jun-11127 Form/Pour Concrete Footings242421-Jun-1126-Jul-11127 Concrete Foundation Walls242425-Jul-1126-Aug-11127 Form and Pour Slab121226-Aug-1114-Sep-11127 Backfill and Compact Walls5513-Sep-1119-Sep-11127 Foundation Phase Complete00 19-Sep-11178 Structure15115119-Sep-1120-Apr-12306 Erect Structural Frame484819-Sep-1125-Nov-11127 Begin Structural Phase0025-Nov-11 418 Floor Decking343425-Nov-1113-Jan-12127 Concrete First Floor363611-Jan-121-Mar-12127 Erect Stairwell and Elevator Walls24241-Mar-124-Apr-12139 Concrete Basement Slab24241-Mar-124-Apr-12139 Concrete Second Floor36361-Mar-1220-Apr-12127 Structure Complete00 20-Apr-12127 Mechanical/Electrical Systems56254914-Apr-11 A26-Jun-130 Rough-In Phase Begins0012-Mar-12 234 Rough In Complete00 5-Feb-130 Elevator2182184-Apr-1212-Feb-1390 Install Elevator Rails and Equipment334-Apr-126-Apr-12217 Install Elevator Cab and Finishes555-Feb-1312-Feb-1391 HVAC56254914-Apr-11 A26-Jun-130 Prepare and Solicit Bids for Heat Pump15214-Apr-11 A4-May-110 Review Bids for Heat Pump10104-May-1117-May-110 Award Contract for Heat Pump6617-May-1125-May-110 Fabricate and Deliver Heat Pump and Controls42242225-May-1123-Jan-130 Install HVAC Ducts242412-Mar-1213-Apr-12186 Insulate Ducts5518-Jun-1225-Jun-12140 Set Heat Pump12124-Jan-1322-Jan-130 Relocate HVAC Chiller7722-Jan-131-Feb-130 Startup and Test HVAC221-Feb-135-Feb-130 Install AC Grills and Registers558-Apr-1315-Apr-1323 Test and Balance HVAC Equipment2221-Jun-1326-Jun-130 Plumbing and Electrical25825820-Jan-1223-Jan-136 Set Mechanical and Electrical Equipment363620-Jan-1212-Mar-12186 Rough-In Plumbing/Piping3324-Aug-1229-Aug-1272 Install Wiring and Cable363631-Aug-1223-Oct-1272 Connect Equipment1122-Jan-1323-Jan-136 Exterior Finishes33628917-Feb-11 A19-Jun-12266 Close-In Phase Begins0015-May-12 296 Building Enclosed00 18-Jun-12127 Brick31226517-Feb-11 A15-May-12124 Assemble Brick Samples0017-Feb-11 A Review and Approve Brick Samples30028-Feb-11 A13-Apr-11 A Prepare and Solicit Bids for Brick Exterior15018-Mar-11 A13-Apr-11 A Review Bids for Brick15008-Apr-11 A28-Apr-11 A Award Contract for Brick5421-Apr-11 A5-May-11377 Deliver Brick115-May-116-May-11377 Brick Exterior Walls171720-Apr-1215-May-12127 Roof242415-May-1219-Jun-12124 Insulation and Built-up Roofing242415-May-1219-Jun-12127 Doors and Windows7727-Apr-128-May-12152 Install Door and Window Frames3327-Apr-121-May-12156 Install Exterior Doors and Windows551-May-128-May-12156 Interior Finishes60155425-Feb-11 A3-Jul-130 Drywall in Offices36365-Feb-1327-Mar-130 Touch-up and Clean-up2219-Jun-1324-Jun-130 Finishes Complete00 26-Jun-130 Punch List5526-Jun-133-Jul-130 Building Addition Complete00 3-Jul-130 Plumbing and Lighting Fixtures44448-Apr-1310-Jun-137 Install Lighting Fixtures778-Apr-1317-Apr-1321 Install Plumbing Fixtures553-Jun-1310-Jun-137 Floor and Carpeting58153425-Feb-11 A4-Jun-130 Assemble and Submit Flooring Samples0025-Feb-11 A Review and Approve Flooring28025-Feb-11 A11-Apr-11 A Prepare and Solicit Bids for Flooring24504-Apr-11 A6-May-11231 Review Bids for Flooring15156-May-1127-May-11231 Award Contract for Flooring5527-May-116-Jun-11231 Fabricate and Deliver Flooring2792793-Jun-116-Jul-12231 Install Floor and Carpeting121216-May-134-Jun-130 Carpentry595927-Mar-1319-Jun-130 Install Ceiling Grid363627-Mar-1316-May-130 Finish Carpentry and Millwork12123-Jun-1319-Jun-130 Paint121214-Feb-134-Mar-1376 Paint Building Interior121214-Feb-134-Mar-1377
Member for
17 years 7 monthsGary its a shame that people
Gary its a shame that people dont help each other i am not ask for the programme i am just asking for the list of activities
List of activities does not belongs to any programme and it is always good to share your experience and best practices you have used.
Those who not share are mostly P6 jockey and I appreciate and salute all those project professional who are helping planning community without thinking about doesn't know how to do their job to stay in a job which they don't deserve,feel it is giving away their experience for free" they all are mean little buggers and they should not be on this forum
Cheers
Member for
17 years 7 monthsWell i am looking for simple
Well i am looking for simple high rise building used as an office upto 20th floor have a curtain wall .
I need some list of Mechanical, Electrical and Plumbing activities
Member for
16 years 7 monthsMuhammad, Most people on this
Muhammad,
Most people on this forum don't share their programmes.
I personally never do, because I feel the programmes I create are the property of my client, and not mine to share.
Other people never do becuase they feel it is giving away their experience for free, when they normally charge for it.
Others don't because they feel it is helping someone who doesn't know how to do their job to stay in a job which they don't deserve.
Some people do share their work but not many, so don't be annoyed or suprised if you don't get what you are looking for.
Member for
15 years 11 monthsHi,There are high rise
Hi,
There are high rise building such as Water Tank Tower with a revolving Restaurant on Top, Guard House Tower Building around a perimeter fence of a Military Compound, Tower buildings such as in Dubai.
The list of activities depends on what is required by the Contract Project.
Regards,
Member for
17 years 7 monthsno reply yet !!!!!!
no reply yet !!!!!!