High Rise Building Schedule

Member for

16 years 3 months

even easier

foundations

1st floor 

2nd floor repeat copy cut paste

Member for

8 years 6 months

hye...anyone can help me..i need example activity shedulling that high rise building such condominium or apartment in 4 block and duration 3 year...please help me..

Member for

17 years 7 months

My gratitude knows no bounds to all those who help me 

Member for

15 years 11 months

 Activity NameOriginal Duration  Design and Engineering51 Design Building Addition23 Design43 Review and Approve Designs9 Assemble Technical Data for Heat Pump3 Review Technical Data on Heat Pumps8  Procurement132 Prepare and Solicit Bids for Heat Pump10 Review Bids10 Prepare and Solicit Bids for Flooring5 Review Bids for Heat Pump2 Review Bids for Flooring3 Award Contract for Heat Pump10 Review Bids for Brick3 Award Contract for Flooring1 Award Contract for Brick2 Fabricate and Deliver Flooring58 Deliver Brick58 Fabricate and Deliver Heat Pump and Controls88  Sitework 114 Site work I50 Sitework95 Site work II45  Foundation79 Foundation64    Excavation24 Begin Building Construction0 Excavation10    Form Work12 Install Underground Water Lines5 Install Storm water lines10    Concrete79 Site Preparation10 Form/Pour Concrete Footings10 Concrete Foundation Walls14 Form and Pour Slab10 Backfill and Compact Walls5 Foundation Phase Complete0  Structure 172 Structure143 Erect Structural Frame40 Begin Structural Phase0 Floor Decking28 Concrete First Floor60 Erect Stairwell and Elevator Walls10 Concrete Basement Slab15 Concrete Second Floor15  Mechanical/Electrical Systems133 Rough-In Phase Begins0 Rough In Complete0  Elevator 165 Elevator138 Install Elevator Rails and Equipment40 Install Elevator Cab and Finishes20  Plumbing and Electrical181 Set Mechanical and Electrical Equipment15 Electrical Costs152 Rough-In Plumbing/Piping45 Install Wiring and Cable45 Connect Equipment3  HVAC 186 HVAC, Plumbing & Fire Protection155 Install HVAC Ducts25 Insulate Ducts2 Set Heat Pump5 Relocate HVAC Chiller3 Startup and Test HVAC1 Install AC Grills and Registers5 Test and Balance HVAC Equipment1  Exterior Finishes278 Exterior Finish Costs205    Brick 266 Assemble Brick Samples3 Review and Approve Brick Samples10 Brick Exterior Walls14    Roof 10 Insulation and Built-up Roofing10    Doors and Windows3 Install Door and Window Frames1 Install Exterior Doors and Windows2  Interior Finishes373 Drywall in Offices15 Interior Finish Costs44 Finishes Phase Begins0 Finishes Milestone0 Touch-up and Clean-up1 Building Addition Complete0 Punch List2    Plumbing and Lighting Fixtures17 Install Lighting Fixtures3 Install Plumbing Fixtures2    Floor and Carpeting362 Assemble and Submit Flooring Samples8 Review and Approve Flooring10 Install Floor and Carpeting5    Carpentry30 Install Ceiling Grid15 Finish Carpentry and Millwork5    Paint 36 Paint Building Interior30

Member for

14 years 7 months

Muhammad you are absolutely right this forum is made to help all planners in our community.

People like Gary don’t understand this. Most of the planners  who write that sort of comments spend most of their office time on internet and rest of the time doing some design plans for desktop surveys.

 If you don’t have any knowledge how do you share something!!! But can give loads of lame excuses.

I hope this example help you. Most people in this forum share their experience because they have knowledge

 

Activity NameOriginal DurationRemaining DurationStartFinishTotal FloatCity Center Office Building Addition68155401-Nov-10 A3-Jul-130  Design and Engineering107001-Nov-10 A06-Apr-11 A     Design Building Addition55001-Nov-10 A19-Jan-11 A     Start Office Building Addition Project0001-Nov-10 A      Review and Approve Designs22017-Jan-11 A17-Feb-11 A     Assemble Technical Data for Heat Pump7016-Feb-11 A25-Feb-11 A     Review Technical Data on Heat Pumps27024-Feb-11 A06-Apr-11 A   Foundation1469823-Feb-11 A19-Sep-11175    Begin Building Construction0028-Feb-11 A      Site Preparation43023-Feb-11 A18-Apr-11 A     Excavation24242-May-116-Jun-11127    Install Underground Water Lines12123-Jun-1121-Jun-11127    Install Underground Electric Conduit12123-Jun-1121-Jun-11127    Form/Pour Concrete Footings242421-Jun-1126-Jul-11127    Concrete Foundation Walls242425-Jul-1126-Aug-11127    Form and Pour Slab121226-Aug-1114-Sep-11127    Backfill and Compact Walls5513-Sep-1119-Sep-11127    Foundation Phase Complete00 19-Sep-11178  Structure15115119-Sep-1120-Apr-12306    Erect Structural Frame484819-Sep-1125-Nov-11127    Begin Structural Phase0025-Nov-11 418    Floor Decking343425-Nov-1113-Jan-12127    Concrete First Floor363611-Jan-121-Mar-12127    Erect Stairwell and Elevator Walls24241-Mar-124-Apr-12139    Concrete Basement Slab24241-Mar-124-Apr-12139    Concrete Second Floor36361-Mar-1220-Apr-12127    Structure Complete00 20-Apr-12127  Mechanical/Electrical Systems56254914-Apr-11 A26-Jun-130    Rough-In Phase Begins0012-Mar-12 234    Rough In Complete00 5-Feb-130    Elevator2182184-Apr-1212-Feb-1390      Install Elevator Rails and Equipment334-Apr-126-Apr-12217      Install Elevator Cab and Finishes555-Feb-1312-Feb-1391    HVAC56254914-Apr-11 A26-Jun-130      Prepare and Solicit Bids for Heat Pump15214-Apr-11 A4-May-110      Review Bids for Heat Pump10104-May-1117-May-110      Award Contract for Heat Pump6617-May-1125-May-110      Fabricate and Deliver Heat Pump and Controls42242225-May-1123-Jan-130      Install HVAC Ducts242412-Mar-1213-Apr-12186      Insulate Ducts5518-Jun-1225-Jun-12140      Set Heat Pump12124-Jan-1322-Jan-130      Relocate HVAC Chiller7722-Jan-131-Feb-130      Startup and Test HVAC221-Feb-135-Feb-130      Install AC Grills and Registers558-Apr-1315-Apr-1323      Test and Balance HVAC Equipment2221-Jun-1326-Jun-130    Plumbing and Electrical25825820-Jan-1223-Jan-136      Set Mechanical and Electrical Equipment363620-Jan-1212-Mar-12186      Rough-In Plumbing/Piping3324-Aug-1229-Aug-1272      Install Wiring and Cable363631-Aug-1223-Oct-1272      Connect Equipment1122-Jan-1323-Jan-136  Exterior Finishes33628917-Feb-11 A19-Jun-12266    Close-In Phase Begins0015-May-12 296    Building Enclosed00 18-Jun-12127    Brick31226517-Feb-11 A15-May-12124      Assemble Brick Samples0017-Feb-11 A        Review and Approve Brick Samples30028-Feb-11 A13-Apr-11 A       Prepare and Solicit Bids for Brick Exterior15018-Mar-11 A13-Apr-11 A       Review Bids for Brick15008-Apr-11 A28-Apr-11 A       Award Contract for Brick5421-Apr-11 A5-May-11377      Deliver Brick115-May-116-May-11377      Brick Exterior Walls171720-Apr-1215-May-12127    Roof242415-May-1219-Jun-12124      Insulation and Built-up Roofing242415-May-1219-Jun-12127    Doors and Windows7727-Apr-128-May-12152      Install Door and Window Frames3327-Apr-121-May-12156      Install Exterior Doors and Windows551-May-128-May-12156  Interior Finishes60155425-Feb-11 A3-Jul-130    Drywall in Offices36365-Feb-1327-Mar-130    Touch-up and Clean-up2219-Jun-1324-Jun-130    Finishes Complete00 26-Jun-130    Punch List5526-Jun-133-Jul-130    Building Addition Complete00 3-Jul-130    Plumbing and Lighting Fixtures44448-Apr-1310-Jun-137      Install Lighting Fixtures778-Apr-1317-Apr-1321      Install Plumbing Fixtures553-Jun-1310-Jun-137    Floor and Carpeting58153425-Feb-11 A4-Jun-130      Assemble and Submit Flooring Samples0025-Feb-11 A        Review and Approve Flooring28025-Feb-11 A11-Apr-11 A       Prepare and Solicit Bids for Flooring24504-Apr-11 A6-May-11231      Review Bids for Flooring15156-May-1127-May-11231      Award Contract for Flooring5527-May-116-Jun-11231      Fabricate and Deliver Flooring2792793-Jun-116-Jul-12231      Install Floor and Carpeting121216-May-134-Jun-130    Carpentry595927-Mar-1319-Jun-130      Install Ceiling Grid363627-Mar-1316-May-130      Finish Carpentry and Millwork12123-Jun-1319-Jun-130    Paint121214-Feb-134-Mar-1376      Paint Building Interior121214-Feb-134-Mar-1377

Member for

17 years 7 months

Gary its a shame that people dont help each other i am not ask for the programme i am just asking for the list of activities 

List of activities does not belongs to any programme and it is always good to share your experience and best practices you have used.

Those who not share are mostly P6 jockey and I appreciate and salute all those project professional who are helping planning community without thinking about doesn't know how to do their job to stay in a job which they don't deserve,feel it is giving away their experience for free" they all are mean little buggers and they should not be on this forum 

Cheers

Member for

17 years 7 months

Well i am looking for simple high rise building used as an office upto 20th floor have a curtain wall .

I need some list of Mechanical, Electrical and Plumbing activities 

Member for

16 years 7 months

Muhammad,

 

Most people on this forum don't share their programmes.

I personally never do, because I feel the programmes I create are the property of my client, and not mine to share.

Other people never do becuase they feel it is giving away their experience for free, when they normally charge for it.

Others don't because they feel it is helping someone who doesn't know how to do their job to stay in a job which they don't deserve.

Some people do share their work but not many, so don't be annoyed or suprised if you don't get what you are looking for.

Member for

15 years 11 months

Hi,

There are high rise building such as Water Tank Tower with a revolving Restaurant on Top, Guard House Tower Building around a perimeter fence of a Military Compound, Tower buildings such as in Dubai.

The list of activities depends on what is required by the Contract Project.

 

Regards,

 

 

Member for

17 years 7 months

no reply yet !!!!!!