A cash flow compares income with expenditure and is best set up on a spreadsheet.
If you want to use the programme however then you have to load the two costs onto each task and then set up a series of progess reports for the required Data dates and assume that you have 100% progress for each task.
Modilisation would be one cost Milestone in the programme.
The two cumulative sums can then be shown on an S Curve.
This would be the basis of future EVA and progress S-Curves.
Resource hours however is a better measure of progress than costs.
Member for
14 years 11 monthsThanks Mike with Your
Thanks Mike with Your Reply!!!!!
I understood what you are saying, but the process is time taking process which will be done for ongoing projects.
Now i require for just to know the tentative cashflows for the tendering purpose. So can you help me in this regard?
Thanks,
Ashik
Member for
19 years 10 monthsHi Ashik A cash flow compares
Hi Ashik
A cash flow compares income with expenditure and is best set up on a spreadsheet.
If you want to use the programme however then you have to load the two costs onto each task and then set up a series of progess reports for the required Data dates and assume that you have 100% progress for each task.
Modilisation would be one cost Milestone in the programme.
The two cumulative sums can then be shown on an S Curve.
This would be the basis of future EVA and progress S-Curves.
Resource hours however is a better measure of progress than costs.
Best regards
Mike Testro