p6 update is based in manhour, than when you update your resources update labor man hour, you can see that whene you change the actual unit in labor man hour you % progress change.
You get to use both, I mean Labor like (Project Manager, Engineers, Mason....etc) and for Non-Labor you can use resource type under any name that will be use in the project like (Loader, Excavetor, Materials...etc).
Member for
13 years 7 monthsHi SUM PUM,p6 update is based
Hi SUM PUM,
p6 update is based in manhour, than when you update your resources update labor man hour, you can see that whene you change the actual unit in labor man hour you % progress change.
Best Regards.
Rafik
Member for
13 years 11 monthshanson CaliforniaThank you
hanson California
Thank you
Member for
13 years 10 monthsHi SUM PUM, You get to use
Hi SUM PUM,
You get to use both, I mean Labor like (Project Manager, Engineers, Mason....etc) and for Non-Labor you can use resource type under any name that will be use in the project like (Loader, Excavetor, Materials...etc).
Please, let me know if you need any more info..
Good Luck..
Hanson