p6 update is based in manhour, than when you update your resources update labor man hour, you can see that whene you change the actual unit in labor man hour you % progress change.

Best Regards.

Rafik

Member for

13 years 10 months

Hi SUM PUM,

You get to use both, I mean Labor like (Project Manager, Engineers, Mason....etc) and for Non-Labor you can use resource type under any name that will be use in the project like (Loader, Excavetor, Materials...etc).

 

Please, let me know if you need any more info..

 

Good Luck..

 