Procedure should be similar within your software. If you want detailed % comparison on activity basis you shall create a comparison baseline updated with progress as if planned to the same DD.
Just remember to compare same % types.
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Wed, 2012-02-01 06:24
The Schedule % Complete will not roll over to summary unless you will load any resource to an activity. Try adding material type resource even with zero value then you will get the summary value.
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Wed, 2012-02-01 01:32
Thanks for this tip, but this schedule% complete does not give overall project summary... it gives updates for the individual activites but does not give overall %age. can we show it from any means?
regards,
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Tue, 2012-01-31 09:31
Member for
21 years 8 monthsProcedure should be similar
Procedure should be similar within your software. If you want detailed % comparison on activity basis you shall create a comparison baseline updated with progress as if planned to the same DD.
Just remember to compare same % types.
Member for
15 years 11 monthsHi, The Schedule % Complete
Hi,
The Schedule % Complete will not roll over to summary unless you will load any resource to an activity. Try adding material type resource even with zero value then you will get the summary value.
Member for
21 years 8 monthsCreate a baseline updated to
Create a baseline updated to same DD using progress as planned and then you shall be able to display both columns.
Member for
13 years 11 monthsThanks for this tip, but this
Thanks for this tip, but this schedule% complete does not give overall project summary... it gives updates for the individual activites but does not give overall %age. can we show it from any means?
regards,
Member for
15 years 11 monthsSchedule % Complete = Planned
Schedule % Complete = Planned % Complete or Baseline % complete
Member for
13 years 11 monthsok, fine but what columns to
ok, fine but what columns to choose in p6? i cannot find baseline or planned %age in p6.
Member for
15 years 11 monthsHi, Al those data are
Hi,
Al those data are available from P6 but you need to export to excell to arrange according to the table you wish.
Regards,