Can we show this table in MS Project or P6?

Member for

21 years 8 months

Procedure should be similar within your software. If you want detailed % comparison on activity basis you shall create a comparison baseline updated with progress as if planned to the same DD.

Just remember to compare same % types.

Photobucket

Member for

15 years 11 months

Hi,

The Schedule % Complete will not roll over to summary unless you will load any resource to an activity. Try adding material type resource even with zero value then you will get the summary value.

Member for

21 years 8 months

Create a baseline updated to same DD using progress as planned and then you shall be able to display both columns.

Member for

13 years 11 months

Thanks for this tip, but this schedule% complete does not give overall project summary... it gives updates for the individual activites but does not give overall %age. can we show it from any means?

regards,

Member for

15 years 11 months

Schedule % Complete = Planned % Complete or Baseline % complete

Member for

13 years 11 months

ok, fine but what columns to choose in p6? i cannot find baseline or planned %age in p6.

Member for

15 years 11 months

Hi,

Al those data are available from P6 but you need to export to excell to arrange according to the table you wish.

 

Regards,