How to produce Histogram & S-curve with Primavera 6

Member for

16 years 3 months

here is the book

add activities

create logic

add a resource to each activity

assign manhours and dollars to each activity 

select view show on bottom resource usage profile

right hand side click right click and select Resource usage profile options on the data tab select either units or costs

this wil give you your histogram

to see your S-curve check the cumulative box