16 years 3 monthshere is the bookadd
here is the book
add activities
create logic
add a resource to each activity
assign manhours and dollars to each activity
select view show on bottom resource usage profile
right hand side click right click and select Resource usage profile options on the data tab select either units or costs
this wil give you your histogram
to see your S-curve check the cumulative box
Member for
17 yearsDear Mr.Rodel MarasiganThx
Dear Mr.Rodel Marasigan
Thx For valuable time, that link is not working
bye,
Member for
19 yearsRE: How to produce Histogram & S-curve with Primavera 6
Ronron,
Click the link below to download the steps which is published on the other thread with same topic and follow the prompt then click Download Now.
Step On How to Produce S-Curve & Histogram