P6, Resource Assignment would not import for repeated resource

Member for

16 years 3 months

go to the projects directory 

make sure that your project is highlighted

Click on the Resources tab

lower right under Resource Assignmets make sure that the box that says Resources can be assigned to the smae activity more than once IS CHECKED.