Oracle Primavera - PM6 Member for 16 years 4 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2017-08-30 13:36 Permalink go to the projects go to the projects directory make sure that your project is highlighted Click on the Resources tab lower right under Resource Assignmets make sure that the box that says Resources can be assigned to the smae activity more than once IS CHECKED. Log in or register to post comments
Member for 16 years 4 months Member for 16 years 4 months Submitted by Zoltan Palffy on Wed, 2017-08-30 13:36 Permalink go to the projects go to the projects directory make sure that your project is highlighted Click on the Resources tab lower right under Resource Assignmets make sure that the box that says Resources can be assigned to the smae activity more than once IS CHECKED.
Member for
16 years 4 monthsgo to the projects
go to the projects directory
make sure that your project is highlighted
Click on the Resources tab
lower right under Resource Assignmets make sure that the box that says Resources can be assigned to the smae activity more than once IS CHECKED.