Progress Update

Member for

13 years 8 months

There are million explanations. As Zoltan said the usual suspect is the Calendar diffrence. specially when you are certain that you didn't change anything else and the diffrence is miniscule.

Here are some of the examples.

1-Calendar diffrence.

2- Holidays, Long weekens, winter restrictions etc

3- Modified logic, original durations, calendars, constraints

4- resource calendar

5- expected finish for in progress activities or extending at completion

 

 

If you are really interested to see what happened add the previous schedule update as the baseline. filter float path 1 and compare start and finish dates with each other along the line.

Member for

16 years 3 months

calendar difference