There are million explanations. As Zoltan said the usual suspect is the Calendar diffrence. specially when you are certain that you didn't change anything else and the diffrence is miniscule.
Here are some of the examples.
1-Calendar diffrence.
2- Holidays, Long weekens, winter restrictions etc
3- Modified logic, original durations, calendars, constraints
4- resource calendar
5- expected finish for in progress activities or extending at completion
If you are really interested to see what happened add the previous schedule update as the baseline. filter float path 1 and compare start and finish dates with each other along the line.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Tue, 2017-07-25 14:31
Member for
13 years 8 monthsThere are million
There are million explanations. As Zoltan said the usual suspect is the Calendar diffrence. specially when you are certain that you didn't change anything else and the diffrence is miniscule.
Here are some of the examples.
1-Calendar diffrence.
2- Holidays, Long weekens, winter restrictions etc
3- Modified logic, original durations, calendars, constraints
4- resource calendar
5- expected finish for in progress activities or extending at completion
If you are really interested to see what happened add the previous schedule update as the baseline. filter float path 1 and compare start and finish dates with each other along the line.