a LOE has a predcesso with a SS and a successor with a a ff and it AUTOMATICALLY calulates the duration betweeen the predcessor start date and the successors finish date.
If you you do not want his then change the activity type.
Member for
19 years
Member for19 years
Submitted by Rodel Marasigan on Thu, 2021-09-30 06:54
Level of Effort (LOE) or Hammock activity is driven by activity relationship. The start of activity should be link to Activity where it needs to start using (SS) Start to Start predecessor and finish is link to Activity where it needs to finish using (FF) Finish to Finish Successor. See sample below:
Member for
19 yearsyw happy to help
yw happy to help
Member for
14 years 4 monthsOk. Thank u Rodel Marasigan
Ok. Thank u Rodel Marasigan
Member for
14 years 4 monthsAlright. Thank u Zoltan Paffy
Alright. Thank u Zoltan Paffy
Member for
16 years 3 monthsyou are missing the whole
you are missing the whole point of a LOE
a LOE has a predcesso with a SS and a successor with a a ff and it AUTOMATICALLY calulates the duration betweeen the predcessor start date and the successors finish date.
If you you do not want his then change the activity type.
Member for
19 yearsHi Suhaila,Level of Effort
Hi Suhaila,
Level of Effort (LOE) or Hammock activity is driven by activity relationship. The start of activity should be link to Activity where it needs to start using (SS) Start to Start predecessor and finish is link to Activity where it needs to finish using (FF) Finish to Finish Successor. See sample below:
LOE activity does not have duration on its own.