Planning, Scheduling & Programming Discussion Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Mon, 2021-05-17 15:13 Permalink Samuel,Once you've identified Samuel, Once you've identified & categorized the major elements of your schedule as advised by Zoltan, you can set up your schedule as shown in this blog post. https://www.plannersplace.com/blog/my-settings-04-schedule-roll-up-in-microsoft-project-p6 The blog post covers Summary Schedule settings in Microsoft Project & Primavera P6. =jerome Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2021-05-17 14:34 Permalink just think of the major just think of the major elements of work and categorize them. use the categories to create the wbs structure then add you activities to that wbs Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2021-05-17 14:33 Permalink just think of the major just think of the major elements of work and categorize them. use the categories to create the wbs structure then add you activities to that wbs Log in or register to post comments
Member for 21 years 9 months Member for 21 years 9 months Submitted by Jerome Odeh on Mon, 2021-05-17 15:13 Permalink Samuel,Once you've identified Samuel, Once you've identified & categorized the major elements of your schedule as advised by Zoltan, you can set up your schedule as shown in this blog post. https://www.plannersplace.com/blog/my-settings-04-schedule-roll-up-in-microsoft-project-p6 The blog post covers Summary Schedule settings in Microsoft Project & Primavera P6. =jerome
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2021-05-17 14:34 Permalink just think of the major just think of the major elements of work and categorize them. use the categories to create the wbs structure then add you activities to that wbs
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Mon, 2021-05-17 14:33 Permalink just think of the major just think of the major elements of work and categorize them. use the categories to create the wbs structure then add you activities to that wbs
Member for
21 years 9 monthsSamuel,Once you've identified
Samuel,
Once you've identified & categorized the major elements of your schedule as advised by Zoltan, you can set up your schedule as shown in this blog post.
https://www.plannersplace.com/blog/my-settings-04-schedule-roll-up-in-microsoft-project-p6
The blog post covers Summary Schedule settings in Microsoft Project & Primavera P6.
=jerome
Member for
16 years 3 monthsjust think of the major
just think of the major elements of work and categorize them.
use the categories to create the wbs structure
then add you activities to that wbs
Member for
16 years 3 monthsjust think of the major
just think of the major elements of work and categorize them.
use the categories to create the wbs structure
then add you activities to that wbs