Oracle Primavera - PM6 Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2019-06-27 14:25 Permalink make it a global resource and make it a global resource and then also use roles so you can assign Joe Shmoe. Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Thu, 2019-06-27 07:00 Permalink For example, Create a For example, Create a Resource Calendar setting the Time 8am-6pm every M-W-F (Department 1), 8am-1pm every T-Th (Department 2). Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2019-06-27 14:25 Permalink make it a global resource and make it a global resource and then also use roles so you can assign Joe Shmoe.
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Thu, 2019-06-27 07:00 Permalink For example, Create a For example, Create a Resource Calendar setting the Time 8am-6pm every M-W-F (Department 1), 8am-1pm every T-Th (Department 2).
Member for
16 years 3 monthsmake it a global resource and
make it a global resource and then also use roles so you can assign Joe Shmoe.
Member for
15 years 11 monthsFor example, Create a
For example, Create a Resource Calendar setting the Time 8am-6pm every M-W-F (Department 1), 8am-1pm every T-Th (Department 2).