Maximum delay of a project in a Month

Member for

16 years 3 months

already answered this on linked in also 

Member for

15 years 11 months

If it falls on the month of Feb 2019 it's 28 calendar days, March 31calendar days, April 30 calendar days.

Member for

16 years 3 months

NO this is a misconception.

lets say I have my steel delivery delayed for more than a month due to where the steel order ended up in the fabrication chain.

Lets say I have a critical procurment item coming from another country and the shipment does not make the boat in time and or the item is held up in customs. It could be months before there is another boat. 

also lets say it rains everyday for 30 days. how long will it take to dry out ? The delay will be 30 days + the dry out time.

Lets say it rains 40 days.