Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2019-01-10 14:05 Permalink fi the schedule is cost fi the schedule is cost loaded and payment is being made off of the cost loaded schedule then yes it would be his responsibility. How else could this possibly happen without him ? Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2019-01-10 14:05 Permalink fi the schedule is cost fi the schedule is cost loaded and payment is being made off of the cost loaded schedule then yes it would be his responsibility. How else could this possibly happen without him ?
Member for
16 years 3 monthsfi the schedule is cost
fi the schedule is cost loaded and payment is being made off of the cost loaded schedule then yes it would be his responsibility. How else could this possibly happen without him ?