You have to consider that there are several types of curves in a certain schedule. At least: Early Curve; Late Curve (based on planned data) and Actual Curve. The Data Date determines where you are at a certain time. And ideally, all data at the left of the data date should be actuals, and everything on the right shall be planned. Of course your calculations shall be based on cumulative weighted percentage that boils down to 100% whether based or using Quantities or Currencies. Each WBS level should have corresponding weight percent as well, which shall come down to 100% with the sum product of activities under it. And the total of all WBS should also come down to 100% which shall represent the whole project. I hope this clears the confusion.

Member for

17 years 7 months

You can use a theoretical S curve equation like:

Y = X / ( X + Exp(C1-C2*X) )

Where C1 and C2 are the parameters to control both: whether the curve is front or back loaded, and the level of knowledge the executor has about the project's subject.

Member for

16 years

I know that but i want to determinate de fonction that gives me the percent function of the number of period ? to draw the s-curve you see ?

Member for

16 years 3 months

activity #1 month #1 = 1320 hours

activity #2 month #2 = 2750 hours

activity #3 month #3 = 3640 hours

actviity #4 month #4 = 2290 hours

Member for

16 years

Sorry for the confusion, I will try to explain, for exemple I have to achive a Task in 4 month with a Manhours of 10000 hours, 

Number of period 4 / period( 1) 13.20% / period( 2) 27.50% / period(3) 36.40% / period(4)  22.90% it means:

The first month my progress need to be 13.20% or 1320 hours and the second month 27.50% it means 2750 hours in period and 4070 hours cumulative .... you see ?

Member for

10 years 5 months

Hi
your calculation period looks like a fiscal year Method, it contains 4 No. Of Quarters in the fiscal year. According to Fiscal year forecast, the assigned period calculation is the achievement of each quarter of the fiscal year. master schedule holds the complete plan of the fiscal year achievement.

Member for

19 years 1 month

It is just linear. For example: X and Y axis or Columns and Rows. Where Columns represent Time or Period (Constants) and Rows represent Scope (or Variables) with corresponding Units, Quantities and Costs (as perhaps you have seen in your BOQ). You simply equate Scope with Time and that's all (period).

Member for

16 years 3 months

percent progress of what ? what is your measuing stick ?

so are you saying for example that you have 100 activities and 50 of them are done then you are 50% complete ?

each activity does not have athe same weighted value in terms of dollars, manhours, commodity units or even duration so you can use that.

Member for

15 years 11 months

As Zoltan says, Cost loaded Schedule will generate the near realistic Forecast and S-Curve.

Otherwise, your Target is Nowhere.

Member for

16 years 3 months

you have not mentioned what the curved is measuing what is the measuing stick ?

why do that  ? why not cost load or manhour load each actvity and let the program draw the curve for you  ?