Rule of Thumb/Best Practice Resource per m2

Member for

16 years 3 months

look up top under the tab entitled build times

there are also several other estimating program but that wokr help you because you need sequence 

order of operations

define your activities 

create the logic

determine quantities

based on the quantities and the standard rate of installation determine the duration based on the number of men that you plan to use for that activity.