Why dont you try to change the activity type using Activity Form.
You need to do a bit of hard work but you will get the result.
Go to View > Activity Form > Type. Change the activity to hammock.
OR:
Filter the selected activities > Open column for Activity Type > type Hammock to 1st activity > Highlight the remaining activities > Edit > Fill Cell. Now you have successfully change the activities to hammock.
Regards.
Member for
21 years 1 month
Member for21 years2 months
Submitted by Jaco Stadler on Wed, 2005-05-25 04:02
Member for
20 years 7 monthsRE: Set activity type hammock for a set of tasks.
Thank you very much. :)
Both ways work. I really said "AHA!!!" when I saw that 5 for hammock. that was what was missing.
I am still looking for a way to get the STYP column to show and be used in a DBF file though.
If you come across that piece of information please send it this way. I will really appreciate it.
Gün. :)
Member for
20 years 8 monthsRE: Set activity type hammock for a set of tasks.
Hi,
Why dont you try to change the activity type using Activity Form.
You need to do a bit of hard work but you will get the result.
Go to View > Activity Form > Type. Change the activity to hammock.
OR:
Filter the selected activities > Open column for Activity Type > type Hammock to 1st activity > Highlight the remaining activities > Edit > Fill Cell. Now you have successfully change the activities to hammock.
Regards.
Member for
21 years 1 monthRE: Set activity type hammock for a set of tasks.
Ok I have not been able to use export with this but what about a global change.
Fisr Copy Your Schedule (If any Thing goes Wrong you have it still)
It is Easy.
First you go to Selection
Select All
Act ID contains L
Act ID contains S
Then you go to Change
Then:STYP EQ 5
Pre Trail Run and see if this is what you needed.
Member for
20 years 7 monthsRE: Set activity type hammock for a set of tasks.
Thank you for the very fast reply. :)
Any chance of doing this from export/import dbf file?
Because the activity.xls file is BIG and takes a very long time to update.
Plus I have had problems with the dates before that I have not been able to solve then. I try to steer away from the activity .xls file.
Gün. :)
Member for
21 years 1 monthRE: Set activity type hammock for a set of tasks.
Try
C:\P3WIN\Samples\EXCEL\ACTIVITY.
This file is also on the p3 CD
Get the Activity’s
Sort the Activity’s
Change the Type to 5 (Hammock en reimport)
And Send back to p3 (Set Activity’s)
PS if you can not get the files PP me your email I will send you the "P3" File