Cumulative budgeted resources

Member for

16 years 3 months

are these LOe activities ?

Member for

7 years 1 month

Resource assignment displays the start and finish date of the resource and it may be different than activity start and finish dates. Probably, those resources are not your primary resoruces and  they do not drive your activity dates, therefore, they may finish later  than activity finish date. You can set your resources dates manually for those activities with respect to your activity dates. 

 

Regards,

Melih 

Member for

7 years 1 month

Resource assignment displays the start and finish date of the resource and it may be different than activity start and finish dates. Probably, those resources are not your primary resoruces and  they do not drive your activity dates, therefore, they may finish later  than activity finish date. You can set your resources dates manually for those activities with respect to your activity dates. 

 

Regards,

Melih