Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2018-06-21 14:21 Permalink unless the job has not unless the job has not started or the job is not finished the actual units will NEVER match the budget oal of these setting below are made in the Project directory go to the projects directory high light your project click on the calculations tab on the right under Resource Assignmenst make sure that under When updating Actual Units or Costs that Subtract Actual from At Completion is checked. Also make sure that Recacluate actula Units and Cost whne duration % coplete changes Also make sure that Link Actual and Atual This Period Units and Cost is checked Also make sure that Link Actual This Period Units and Cost is checked On the Resoures tab on the right hand side Under Assignmnets Defaults that under Resource Assignments that Resources can be assigned to teh same actviity more than once IS NOT CHECKED on the left under Activities make sure that Link Budget and At Completion for actvities not started activites is checked. Log in or register to post comments
Member for 16 years 3 months Member for 16 years 3 months Submitted by Zoltan Palffy on Thu, 2018-06-21 14:21 Permalink unless the job has not unless the job has not started or the job is not finished the actual units will NEVER match the budget oal of these setting below are made in the Project directory go to the projects directory high light your project click on the calculations tab on the right under Resource Assignmenst make sure that under When updating Actual Units or Costs that Subtract Actual from At Completion is checked. Also make sure that Recacluate actula Units and Cost whne duration % coplete changes Also make sure that Link Actual and Atual This Period Units and Cost is checked Also make sure that Link Actual This Period Units and Cost is checked On the Resoures tab on the right hand side Under Assignmnets Defaults that under Resource Assignments that Resources can be assigned to teh same actviity more than once IS NOT CHECKED on the left under Activities make sure that Link Budget and At Completion for actvities not started activites is checked.
Member for
16 years 3 monthsunless the job has not
unless the job has not started or the job is not finished the actual units will NEVER match the budget
oal of these setting below are made in the Project directory
go to the projects directory
high light your project
click on the calculations tab
on the right under Resource Assignmenst make sure that under When updating Actual Units or Costs that Subtract Actual from At Completion is checked.
Also make sure that Recacluate actula Units and Cost whne duration % coplete changes
Also make sure that Link Actual and Atual This Period Units and Cost is checked
Also make sure that Link Actual This Period Units and Cost is checked
On the Resoures tab on the right hand side Under Assignmnets Defaults that under Resource Assignments that
Resources can be assigned to teh same actviity more than once IS NOT CHECKED
on the left under Activities make sure that Link Budget and At Completion for actvities not started activites is checked.