there is NO STANDARD rate and MAx units/time you set this based on your resources how they work together is that is you set price per unit to $2/LF and if you have 5 LF of whatever units that will make the costs $2*5=$10
Budgeted costs was already expalined above this will give you your budgeted costs based on the quantity of units.
default units/time & Max units can changed based on the resource being used. Maybe one resource is working 10 hours per day and another is working 8 hours per day.
Member for
16 years 3 monthsthere is NO STANDARD rate and
there is NO STANDARD rate and MAx units/time you set this based on your resources how they work together is that is you set price per unit to $2/LF and if you have 5 LF of whatever units that will make the costs $2*5=$10
Budgeted costs was already expalined above this will give you your budgeted costs based on the quantity of units.
default units/time & Max units can changed based on the resource being used. Maybe one resource is working 10 hours per day and another is working 8 hours per day.