WBS Duration is not same as Activity Duration

Member for

16 years 3 months

just by changing the project to a deflaut calendar this only applies when adding NEW activities. For all of the existing activities they are still on the original calendar assigned to them. You have to ASSIGN the existing activities to the default calendar. Add a column for calendar, filter for ALL, in the calendar column for the first activity at the top select the default claendar and then do a fill down, now re-schedule your project. 

It is ALWAYS a 2 step process adding a calendar does NOTHING until you ASSIGN  the activities to that calendar and recalculate the schedule.

Member for

16 years 3 months

just by changing the project to a deflaut calendar this only applies when adding NEW activities. For all of the existing activities they are still on the original calendar assigned to them. You have to ASSIGN the existing activities to the default calendar. Add a column for calendar, filter for ALL, in the calendar column for the first activity at the top select the default claendar and then do a fill down, now re-schedule your project. 

It is ALWAYS a 2 step process adding a calendar does NOTHING until you ASSIGN  the activities to that calendar and recalculate the schedule.

Member for

7 years 11 months

Hi everybody ,

I am a new user of Primavera.

I am facing an issue regarding total duration of a project which is showing two different duration in two systems. I have imported this project to the second system from the first One where it was created.

I have changed defaulf calender and made it same for both the projects .Still it didnt make any difference.

Later i made unit of time in User Preference as same for the both the projects .

It would be very helpful if somebody can help me to solve this issue..

Vipin

Member for

16 years 7 months

Ashik,

1)

Go to Enterprise menu > calendars

Scroll down until you find the calendar which has a tick in the "default" column

Is this the same calendar used on ALL activities within the Main Plant, Covered Structure & Finishes and Sub Structure Completion WBS?

 

2)

Got to Edit menu > User preferences

Set the unit of time for durations to "hour"

Is the duration of your WBS still incorrect?

Member for

14 years 10 months

Mr.Gary,

Thanks for your reply.

If you see in my above posted schedule, the dates are showing same as the sub activities but the duration is not correct.

I have checked the calenders also, even it shows 7 days/week as working days.

Your posted presentation is very useful but i didnt get solution for this question.

I have seen the WBS used by in Calenders also, It shows properly.

Kindly revert back to me

Ashik