Adding Activities after the baseline is set

Member for

16 years 3 months

you dont the baseline stay as is never ever to be touched this is your measuring stick to which progress will be measured against. 

When comparing the baseline to the current schedule it will show that the new activites are not in the baseline. This is excalty what you want bcasue you want to show that they were added or not in the originla scope of work. 

its like saying I need to lose 10 lbs the first thing that I have to do is to get on a scale and weigh nyself. Thsi not becomes my baseline or reference point. I will I ever know if I am loosing weight if I keep moving the target andf I have nothing to measure against ?

Member for

8 years

How to see the planned progress % for the secondary baseline. What column need to be added.

Member for

18 years 6 months

Hi Eljaro,



Let us consider that baseline programme was already approved by the Client.



In order to update the Budgeted Planned you need to update the resources which was assigned to your newly added activities and incorporate this new quantity to your current programme.



Regards.






Member for

17 years 7 months

Thanks,



Now lets say I generated the s-curve on an excel spreadsheet. Do I now change the planned % to those reflected on my updated baseline.



This means my next report will show an entire different curve compared to my last report update.



Wouldnt it be nice if the scope guys could just stick to the plan :-(



Arnold, could you also send me that P6 curve snapshot.



eljarowalters@yahoo.com

Member for

18 years 6 months

Hi Eljaro,



You need to update your Baseline. To do this, follow the following steps:



1. Go to project --> Maintain Baselines

2. Select update

3. Tick "Add new activities and activity data (except actual)" & "Update exisiting activities already in the baseline"

4. and tick the other depending on your requirements.

5. Then select "Update"



HTH.



Regards,



Arnold