Our client doesn't want to see overallocated resources in the programme. So that's why I wanted to know the standard practice in the industry, wheather it is common to show overallocated resources in the programme or not.
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Tue, 2017-04-04 13:17
I would choose #1 not only to show the over utilization but to know when you can remove one or more of the excavators off site. Paying for rental or being idel on a project is a wste of money. Send that unused excavator off site to another project to stop the charges.
Member for
16 years 3 monthsthen just turn the over
then just turn the over allocation bar off
Member for
24 years 8 monthsI don't understand your
I don't understand your problem.
You can enter the number of available excavators and level your schedule.
Member for
8 years 8 monthsOur client doesn't want to
Our client doesn't want to see overallocated resources in the programme. So that's why I wanted to know the standard practice in the industry, wheather it is common to show overallocated resources in the programme or not.
Member for
16 years 3 monthsI would choose #1 not only to
I would choose #1 not only to show the over utilization but to know when you can remove one or more of the excavators off site. Paying for rental or being idel on a project is a wste of money. Send that unused excavator off site to another project to stop the charges.