Primavera P6

Member for

16 years 4 months

your TIMES are not correct and or your remaining durations are in fractions of days not whole days,  Edit users preference,  Click on the Dates Tab , Click show minutes (12 hour) Click on the Time Units Tab, Next under the Duration Format Unit of Time Decimals change this value to 2 Decimals, If you see any Original Durations and or Remaining Durations with decimals round them up or down and change them to whole numbers.

Go to the project directory click on dates make sure your project start TIME to 8:00 am or the earliest time in your calendar. Change the data date TIME to 8:00 am or the earliest time in your calendar. Change the Project Must Finish by date TIME to 5:00 pm or the LATEST times in your calendars. If you have any start constraints TIME to 8:00 am or the earliest time in your calendar. If you have any finish constraints TIME to 5:00 pm or the LATEST times in your calendars. Any activities that are inprogress make sure that the start TIME is  8:00 am or the earliest time.

Now when you progress the schedule make sure that any actual start TIMES are 8:00 am or the earliest time in your calendar.

if you have any actual finish dates make sure that the TIME is set to 5:00 pm or the LATEST times in your calendars.

Member for

21 years

Usually this is a calendar issue, the activities may be on differnet calendars

 

Also remember that P6 calculates in hours - not days - so viewing decimal places in durations may be helpful