In my role as delay analyst I get to review contractor's programmes on a regular basis and in my experience about 5% can be deemed fit for purpose in time management of construction projects.
In an earlier PP post I set up a discussion on the topic of "Ban These Planning Abominations" which is still worth reading.
Wishing you a succesful and productive retirement.
Member for
19 years 10 monthsHi PeterIn my role as delay
Hi Peter
In my role as delay analyst I get to review contractor's programmes on a regular basis and in my experience about 5% can be deemed fit for purpose in time management of construction projects.
In an earlier PP post I set up a discussion on the topic of "Ban These Planning Abominations" which is still worth reading.
Wishing you a succesful and productive retirement.
Best regards
Mike Testro