Level 1 House Building Durations and Completion Rates

Member for

9 years

Mike,

Thank you.

There is very little information at this stage e.g. I have planning application info on just under 100 units, and unit types only for the remainder.

I have only recently started as an Assistant Planner, so while I could probably produce a detailed construction programme, to do so for a scheme of this size, with no information is beyond my capabilities at current - especially within the timeframes. It would probably take me weeks!

Is starting from detail and working to summary the only reliable method for establishing an early programme?

Kind regards,

Tom

Member for

19 years 10 months

Hi Tom - Welcome to planning planet.

Stop guessing and do it properly with a level 4 bottom up programme using FS links.

If you have Asta PowerProject use the Line of Balance feature to create a Time/Distance programme to get the whole site on 1 A3 sheet.

Best regards

Mike Testro