P6 Schedule with Budgeted Labor Unit

Member for

10 years 7 months

Deleted posted twice

Member for

10 years 7 months

Thanks David for your reply..

If you got some time i will send you the XER file and you can take a look at that...

 

Actually the program is made by other planner but now iam supposed to update it and get the status..But when i put activity % to the program nothing is changed at the WBS level...Hope you can understand the case with my broken english.This is my Email ID siddiq.ahmed86@gmail.com if you send me a test mail i will send you the XER

 

Siddiq.

Member for

21 years

siddiq,

 

You must assign a cost to the resource, as P6's "Performance % complete" only rolls-up cost, not quantity. Of course if every resource is priced at $1.00 per unit then effectively they are the same thing. The % compete value you want  is Performance % complete for the current schedule ( effectively BCWP) and from the baseline Schedule % complete (effectively BCWS)