As per the hammock or Level of Effort method you suggested, I believe that the hammock activity progress will be calculated based on the remaining duration and it may not match with the real drawings submitted and approved.
So I have the opinion that it can be calculated with EV method as follows;
1. Consider the budget of shop drawings as 60%for submittal and 40% for approval.
2.Create the WBS as below;
Shop Drawings Submission & Approval
Submission
Civil
Mech
Elect
and similar for Approval as well.
3. Assign the above said budget value for each activity.
4. While updating the project, input the progress value considering the revisions and approvals.
The updated programme will show the rolled-up summary.
As per the hammock or Level of Effort method you suggested, I believe that the hammock activity progress will be calculated based on the remaining duration and it may not match with the real drawings submitted and approved.
So I have the opinion that it can be calculated with EV method as follows;
1. Consider the budget of shop drawings as 60%for submittal and 40% for approval.
2.Create the WBS as below;
Shop Drawings Submission & Approval
Submission
Civil
Mech
Elect
and similar for Approval as well.
3. Assign the above said budget value for each activity.
4. While updating the project, input the progress value considering the revisions and approvals.
The updated programme will show the rolled-up summary.
Regards
Kannan
Member for
14 years 11 months
Member for15 years
Submitted by sb_sunil2000 on Mon, 2016-07-25 08:04
First of all make the activities such as Civil shop drawings, Mechanical shop drawings, Electrical shop drawings etc. Then create a hammock, add individual percentages for each activity. Hammock bar will show the overall percentage. Then you will be able to judge the 20% milestone.
In my opinion you need to agree with client how to quantify or define the percentage of shop drawings.
For eg: Civil has 50 SDs, Mechanical 25SDs and Electrical 25SDs. Based on construction works, you need to prioritize the sequence of drawings for each discipline. Then identify the completion date of 20% SDs for each discipline. Assign a resource for that activity, say-SOP and assign the 20% cost to that activity.
There may be the problem to calculate the progress with the above method. Because with the payment milestone, you can show the progress- only when you achieve the milestones, not during the time of execution.
BR
Kannan
Member for
11 years 7 months
Member for11 years7 months
Submitted by vinodkailasg on Wed, 2016-06-29 12:26
Depends on the way you will measure these percents.
What is 80% of procurement?, what is 20% of shop drawings?
Please specify your software. I can advise how it could be modeled in Spider Project but if you use another software it is useless because the same methods are not supported by other tools.
Member for
17 years 4 monthsHi Mike & SunilAs per the
Hi Mike & Sunil
As per the hammock or Level of Effort method you suggested, I believe that the hammock activity progress will be calculated based on the remaining duration and it may not match with the real drawings submitted and approved.
So I have the opinion that it can be calculated with EV method as follows;
1. Consider the budget of shop drawings as 60%for submittal and 40% for approval.
2.Create the WBS as below;
Shop Drawings Submission & Approval
Submission
Civil
Mech
Elect
and similar for Approval as well.
3. Assign the above said budget value for each activity.
4. While updating the project, input the progress value considering the revisions and approvals.
The updated programme will show the rolled-up summary.
Regards
Kannan
Member for
17 years 4 monthsHi Mike & SunilAs per the
Hi Mike & Sunil
As per the hammock or Level of Effort method you suggested, I believe that the hammock activity progress will be calculated based on the remaining duration and it may not match with the real drawings submitted and approved.
So I have the opinion that it can be calculated with EV method as follows;
1. Consider the budget of shop drawings as 60%for submittal and 40% for approval.
2.Create the WBS as below;
Shop Drawings Submission & Approval
Submission
Civil
Mech
Elect
and similar for Approval as well.
3. Assign the above said budget value for each activity.
4. While updating the project, input the progress value considering the revisions and approvals.
The updated programme will show the rolled-up summary.
Regards
Kannan
Member for
14 years 11 monthsHi Vinod,First of all make
Hi Vinod,
First of all make the activities such as Civil shop drawings, Mechanical shop drawings, Electrical shop drawings etc. Then create a hammock, add individual percentages for each activity. Hammock bar will show the overall percentage. Then you will be able to judge the 20% milestone.
Best Regards,
Sunil Babu
Member for
19 years 10 monthsHi VinodPut all your shop
Hi Vinod
Put all your shop drawing tasks under a hammock.
As each drawing is completed the cumulative progress will be shown on the hammock bar.
You will see when 20% is reached.
Best regards
Mike Testro
Member for
17 years 4 monthsHi Vinod,In my opinion you
Hi Vinod,
In my opinion you need to agree with client how to quantify or define the percentage of shop drawings.
For eg: Civil has 50 SDs, Mechanical 25SDs and Electrical 25SDs. Based on construction works, you need to prioritize the sequence of drawings for each discipline. Then identify the completion date of 20% SDs for each discipline. Assign a resource for that activity, say-SOP and assign the 20% cost to that activity.
There may be the problem to calculate the progress with the above method. Because with the payment milestone, you can show the progress- only when you achieve the milestones, not during the time of execution.
BR
Kannan
Member for
11 years 7 monthsSoftware used is Primavera P6
Software used is Primavera P6 (15.2)
Suppose there schedule of Payment is like below :
1. Complete 20% Shop Drawings
2. Complete 60% Shop Drawings
3. Complete 100% Shop Drawings
But the main issue is shop drawings are breakdown into discipline wise and how we will relate this shop drawing progress to this SOP milesone.
I have to complete SOP 1 when 20% of Shop Drawings are completed. How to relate this milestone to Shop drawing progress.
Member for
24 years 9 monthsDepends on the way you will
Depends on the way you will measure these percents.
What is 80% of procurement?, what is 20% of shop drawings?
Please specify your software. I can advise how it could be modeled in Spider Project but if you use another software it is useless because the same methods are not supported by other tools.