Planning, Scheduling & Programming Discussion Member for 17 years 4 months Member for 17 years 5 months Submitted by Kannan CP on Mon, 2016-04-11 15:11 Permalink Hi Danielle,In the WBS Hi Danielle, In the WBS section, set the ETC as follows; ETC= PF*(Budget at Compl- Earned Value) & PF=1. Now in the Activity Usage Spread Sheet, use the Estimate to Complete Labour units, instead of Remaining Labour units. Remaining LU will be calculated only based on the actual units, which you may need to type manually. Best Regards Kannan Log in or register to post comments
Member for 17 years 4 months Member for 17 years 5 months Submitted by Kannan CP on Mon, 2016-04-11 15:11 Permalink Hi Danielle,In the WBS Hi Danielle, In the WBS section, set the ETC as follows; ETC= PF*(Budget at Compl- Earned Value) & PF=1. Now in the Activity Usage Spread Sheet, use the Estimate to Complete Labour units, instead of Remaining Labour units. Remaining LU will be calculated only based on the actual units, which you may need to type manually. Best Regards Kannan
Member for
17 years 4 monthsHi Danielle,In the WBS
Hi Danielle,
In the WBS section, set the ETC as follows;
ETC= PF*(Budget at Compl- Earned Value) & PF=1.
Now in the Activity Usage Spread Sheet, use the Estimate to Complete Labour units, instead of Remaining Labour units.
Remaining LU will be calculated only based on the actual units, which you may need to type manually.
Best Regards
Kannan