Revised Baseline Programme

Member for

12 years 6 months

Thanks for your reply. I will follow the same....

Member for

12 years 6 months

Thanks for your reply. I will follow the same....

Member for

16 years 3 months

number 1 

if you have been updating the schedule on a consistant basis ALL of the actulas should be in the schedule. Then siimply revise any logic for activities not yet started. What happened in the past are actuals and the EOT for 3 months was recognized. So change the project must finish by date and or change the finish on or before date on the project finish milestone activity by 3 months.