Ufuk,

Follow the steps below.

  • Create 3 UDFs as shown in screenshot below



    [[wysiwyg_imageupload:3208:]]
  • Create a Global Change using the the 3 UDFs created above. Remember to replace 19-Jul-99 with your project start date and apply the Global Change



    [[wysiwyg_imageupload:3209:]]
  • Add 2 columns to your schedule for Start Day & Finish Day using the UDFs user_integer_1 & user_integer_2



    [[wysiwyg_imageupload:3211:]]
  • Voila, your ordinal dates should now be visible on your schedule



    [[wysiwyg_imageupload:3212:]]

 

=jerome

Member for

9 years 10 months

These data do not appear at my primavera (P6 R8.3.2), still couldn' t find a way for this ...

Member for

9 years 10 months

These data do not appear at my primavera (P6 R8.3.2), still couldn' t find a way for this ...

Member for

21 years 9 months

Under Global Change, you should find these fields under the "Then" section parameter. See attached screenshots.

 

[[wysiwyg_imageupload:3206:]]

[[wysiwyg_imageupload:3207:]]

Member for

9 years 10 months

I have tried, I checked my primavera but couldn' t see any "user_start_date1" or "user_integer1" etc. How can we create these.

Thank you,

Member for

9 years 10 months

Amro thanks for your answer, there was ordinal dates column available at previous versions but it is not available at the latest version, I guess.  I can hide the dates columns but I have to show ordinal days ...

Member for

9 years 10 months

Amro thanks for your answer, there was ordinal dates column available at previous versions but it is not available at the latest version, I guess.  I can hide the dates columns but I have to show ordinal days ...

Member for

16 years 10 months

Hi,

my suggestion to you to show in Gantt chart and just hide  colums of dates on activity table .

Because in User Preference this not available option.

 

 

Thanks