If you have calculated the number of hooks required on a spreadsheet you will also know the tasks in your programme that need cranage.
I create a permanent resource called "hooks" and allocate the number required to each task. I then run a histogram to see if the programmed hooks excede the maximum number at any given time.
With this information you will be informed of upcoming bottlenecks and arrange accordingly.
Avoid the temtation to run a resource levelling option on hooks because this will screw up your programme in nano seconds.
Member for
19 years 10 monthsHi Daren - Welcome to
Hi Daren - Welcome to Planning Planet
Next time please only tap the "save" button once.
If you have calculated the number of hooks required on a spreadsheet you will also know the tasks in your programme that need cranage.
I create a permanent resource called "hooks" and allocate the number required to each task. I then run a histogram to see if the programmed hooks excede the maximum number at any given time.
With this information you will be informed of upcoming bottlenecks and arrange accordingly.
Avoid the temtation to run a resource levelling option on hooks because this will screw up your programme in nano seconds.
Best regards
Mike Testro