making a summary programme

Member for

14 years 11 months

Hi Janaka,

First create a summary programme based on contractors programme of works.

Fix the contractual dates as milestones. Link the Engineering and procurement properly.Create a baseline and update the progress as per the current status. Schedule the programme with latest datadate then you can see the realistic probable finish date of the programme. Compare with the baseline to track the dalayed areas of work . Do necessary acceleration.

Best Regards,

Sunil

Member for

16 years 11 months

Hi Janaka,

One of the way, is to update the contractor's schedule of works.Add a new WBS, with a set of key milestones (Required/Requested by Client for delay notification) logically linked with the updated contractor's schedule and then collapse the full Schedule in to high level WBS.

 

Cheers

Shahul Badhusha