I think taht you didint got my point,what i need is to put all money for same activity in one month not devide according to days,If the activity start on Jan an finish in Feb , I need to assighn all budget cost in Jan,no to make part in Jan and part in Feb
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Sun, 2014-06-29 07:18
Member for
15 years 11 monthsYes, absolutely I did not get
Yes, absolutely I did not get your point.
In my understanding now, you want the Assignment to be eitheir on the Fist Day or at the End of the activity Duration.
I suggests Make use of the Resource Curve.
Member for
11 years 9 monthsI think taht you didint got
I think taht you didint got my point,what i need is to put all money for same activity in one month not devide according to days,If the activity start on Jan an finish in Feb , I need to assighn all budget cost in Jan,no to make part in Jan and part in Feb
Member for
15 years 11 monthsUse the Ordinal Date in the
Use the Ordinal Date in the Timescale....