The issue why you are getting the same value with the current schedule (Updated Schedule) against your baseline is sometimes because of the Assign Baselines... as shown in the image below: It sometimes happen that you assigned Project Baseline or User Baseline (e.g. Primary), however in your Project Settings, the one selected is the User's Primary Baseline or the other way around. Make sure that they are consistent each other. Likewise, make use of the correct Terms/Table (BL Project representing Project Baseline, BL1 representing Primary Baseline, so on and so forth)..
[[wysiwyg_imageupload:1739:]]
[[wysiwyg_imageupload:1740:]]
Thank you
Cheers,
Arnold
Member for
17 years 9 months
Member for17 years9 months
Submitted by Ronnel Anthony… on Tue, 2013-08-13 09:49
Thanks for your insights, Early this morning while reading your inputs i tried making the baseline schedule into a baseline in itself. and guess what i got.. different values.. how come the same exported and re-imported baseline would yield difference, yet when using the claim digger to search for changes, the claim digger would yield no changes at all. So, things are quite strange lately. (i did a screenshot of the event and will save it as a reference)
Well, i tried restoring the baseline and removing it from the comparison and later on tried assigning the same baseline and repeating the same comparison i did earlier.. and guess what.. the cost curves are now identical. and again i tried restoring the baseline and assigned it to the updated schedule and this time, the values of the baseline via the cost curve are correct.
I guess this is one of the strangest P6.7 Glitches that i have encountered. I thank you for your effort in answering my post eventhough it sounds so strange.
This thing that happend is very strange and beyond my comprehension. i am glad that somehow it went well after all.
Thank you so much,
Ronnel Anthony Celerio
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Mon, 2013-08-12 09:40
In the Initial Baseline Schedule, Budgeted Cost of Resources is where the Cost Curves was derived.
In the Updated Schedule with a Baseline Attached (Initial Baseline), Cost Data of the Initial Baseline's Resources are not appearing in that Updated Schedule.
The Budgeted Cost of the Resources of the updated schedule shall be the same as the Budgeted Cost of the same Resources in the Initial Baseline.
Budgeted COst of the Updated Schedule changes due to the the following but not limited to "Duration Type" setting and "Resource Calendar" Setting.
In the Updated Schedule, what data you are referring to compare with the Budgeted Cost of the Initial Baseline?
Regards,
Member for
17 years 9 months
Member for17 years9 months
Submitted by Ronnel Anthony… on Mon, 2013-08-12 08:51
Good day, i compared the Cost curve of the Initial schedule vs the attached baseline cost curve on the updated schedule 4 months after.
Correct me if i am wrong but comparing baseline with planned values (budgeted) would yield different chart values (cost & labor). because the planned values would be the reflection of the latest schedule update.
I am comparing and noticing changes from the inithial schedule (baseline) vs the attached baseline curve on a updated schedule. i just dont know how it would have changes..
Thank you. i hope you can shed light on this.
Regards,
Ronnel Anthony Celerio
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Sun, 2013-08-11 06:08
Member for
11 years 8 monthsHi every body Iam new to this
Hi every body Iam new to this site , we have to continue our understanding by transfering the information.
Member for
18 years 6 monthsYou are most welcome Ronnel,
You are most welcome Ronnel, I will be glad to help..
Member for
17 years 9 monthsThanks Arnold for your
Thanks Arnold for your insights.. i checked the settings and both settings are the same.. Thank you for the heads up.
Thanks again..
Member for
18 years 6 monthsHi Ronnel,The issue why you
Hi Ronnel,
The issue why you are getting the same value with the current schedule (Updated Schedule) against your baseline is sometimes because of the Assign Baselines... as shown in the image below: It sometimes happen that you assigned Project Baseline or User Baseline (e.g. Primary), however in your Project Settings, the one selected is the User's Primary Baseline or the other way around. Make sure that they are consistent each other. Likewise, make use of the correct Terms/Table (BL Project representing Project Baseline, BL1 representing Primary Baseline, so on and so forth)..
[[wysiwyg_imageupload:1739:]]
[[wysiwyg_imageupload:1740:]]
Thank you
Cheers,
Arnold
Member for
17 years 9 monthsRaymund,Thanks for your
Raymund,
Thanks for your insights, Early this morning while reading your inputs i tried making the baseline schedule into a baseline in itself. and guess what i got.. different values.. how come the same exported and re-imported baseline would yield difference, yet when using the claim digger to search for changes, the claim digger would yield no changes at all. So, things are quite strange lately. (i did a screenshot of the event and will save it as a reference)
Well, i tried restoring the baseline and removing it from the comparison and later on tried assigning the same baseline and repeating the same comparison i did earlier.. and guess what.. the cost curves are now identical. and again i tried restoring the baseline and assigned it to the updated schedule and this time, the values of the baseline via the cost curve are correct.
I guess this is one of the strangest P6.7 Glitches that i have encountered. I thank you for your effort in answering my post eventhough it sounds so strange.
This thing that happend is very strange and beyond my comprehension. i am glad that somehow it went well after all.
Thank you so much,
Ronnel Anthony Celerio
Member for
15 years 11 monthsRonnel,In the Initial
Ronnel,
In the Initial Baseline Schedule, Budgeted Cost of Resources is where the Cost Curves was derived.
In the Updated Schedule with a Baseline Attached (Initial Baseline), Cost Data of the Initial Baseline's Resources are not appearing in that Updated Schedule.
The Budgeted Cost of the Resources of the updated schedule shall be the same as the Budgeted Cost of the same Resources in the Initial Baseline.
Budgeted COst of the Updated Schedule changes due to the the following but not limited to "Duration Type" setting and "Resource Calendar" Setting.
In the Updated Schedule, what data you are referring to compare with the Budgeted Cost of the Initial Baseline?
Regards,
Member for
17 years 9 monthsRaymund,Good day, i compared
Raymund,
Good day, i compared the Cost curve of the Initial schedule vs the attached baseline cost curve on the updated schedule 4 months after.
Correct me if i am wrong but comparing baseline with planned values (budgeted) would yield different chart values (cost & labor). because the planned values would be the reflection of the latest schedule update.
I am comparing and noticing changes from the inithial schedule (baseline) vs the attached baseline curve on a updated schedule. i just dont know how it would have changes..
Thank you. i hope you can shed light on this.
Regards,
Ronnel Anthony Celerio
Member for
15 years 11 monthsRonnel, I would ask you if
Ronnel,
I would ask you if you compare baseline values with planned values?
Regards,