Project resumption after long time of stoppage

Member for

12 years 5 months

many thanks 

Member for

19 years 10 months

Hi Sabry

In that case use the calendar.

Best regards

Mike Testro

Member for

12 years 5 months

yes i know but i want show that in that period work was stoped

Member for

19 years 10 months

Hi Sabry

Another way is to set a progress data date at the time of restart with the same progress on tasks when stopped or 0% progress for work yet to start.

The calendar method would also work OK.

Best regards

Mike Testro