It should be derived based on the relative weightage in the overall manhours. It depends on the nature of activity. For example plastering work against 100 man-hours, you can distribute this manhours as 75% to Mason and 25% to Helper (Labors) i.e. the job requires 75 man- hours of Mason and 25 man-hours of Labor.
Member for
17 years 2 monthsIt should be derived based on
It should be derived based on the relative weightage in the overall manhours. It depends on the nature of activity. For example plastering work against 100 man-hours, you can distribute this manhours as 75% to Mason and 25% to Helper (Labors) i.e. the job requires 75 man- hours of Mason and 25 man-hours of Labor.