Top 10 Primavera Interview questions and Model Answers

Member for

10 years 1 month

Answer no:-3 critical path activity has a minimum duration of time, in critical activity float will be zero(0) means we cant delay date of that activity because float is zero(0) mean there will not any flexibility.thats why called a Critical path activity.

Member for

16 years 7 months

Q2:What is a constraint in primavera?

Constrains in primavera is to fix the early or late start or finish date of an activity as per following options:

1) Project Must Finish by

2) Mandatory Start / Mandatory Finish

3) Start / Finish On or After

4) Start / Finish On or Before

5) Start / Finish On

6) Expected Finish

7) ALAP

 

Q3:How can you define the Critical Path in primavera?

The sequence of activities which describe the longest path from the data date to the end of the project. In a schedule without any constraints, this will be all activities with zero total float.

(if you have constrains which force negative float, simply filtering on total float equal to or less than zero can bring up activities which are not on the critical path)

 

Q7:How do u measure & compare the progress using primavera?

Progress is measured primarily against the baseline.  If the baseline has been loaded with cost and/or resources, earned value management can be used for this purpose. If not, progress is measured as variance to baseline dates.

Other progress measurement techniques also exist –for example Earned Schedule.

 

Q9:What is an S – Curve and how to create S Curve in primavera?

An S-curve is a graph showing cumulative cost or value (measured in terms of money or manhours) against time. On a typical project, these graphs follow an “S” shape, hence the name. Typical data to be plotted on an S-Curve includes:

Actual Cost (ACWP)

Planned Value (BCWS) –Early dates

Planned Value (BCWS) –Late dates

Earned Value (BCWP)

Forecast Value –Early dates

Forecast value –Late dates

Forecast Cost –Early dates

Forecast cost –Late dates

 

(it’s not a histogram. –A histogram is a bar graph of the in-period values. the S-curve is the line-graph of the cumulative values)

 

Member for

17 years 8 months

Thanks gray for your input, what you think the complete and correct answer are ?

Member for

16 years 7 months

Answers to questions 2 & 7 are incomplete

 

Answers to questions 3 & 9 are incorrect