As most the building related work is related to concrete, we usually calculate using m3 / mday. If needed, m3 / eqpt to show the needs for concrete pumps, vibrators.
Will not split into rebar, formwork. Calculate these together in its entirety. Do take note of the 72 hours allowance for formwork stripping if needed.
Member for
21 years 1 monthHi,I will do so for my own
Hi,
I will do so for my own project
Excavation - m3 / mday or m3 /eqpt
Bored pile - lm / mday
Pilecap - No./mday (not sure)
Raft Slab - m3 / mday or m3 /eqpt
Ground beam - m3 / mday or m3 /eqpt
Column - m3 / mday or m3 /eqpt
Slab - m3 / mday or m3 /eqpt
As most the building related work is related to concrete, we usually calculate using m3 / mday. If needed, m3 / eqpt to show the needs for concrete pumps, vibrators.
Will not split into rebar, formwork. Calculate these together in its entirety. Do take note of the 72 hours allowance for formwork stripping if needed.