Urgent help - Project extraction from baseline

Member for

13 years 11 months

Thanks Gary.

It really helped. Eastiest way. Thanks a lot.

And Rafael, I appreciate your reply, it was really an additional information. Thanks

Regards,

Sivaganesh,S

Member for

21 years 8 months

The easiest way would be to look on the Backup. A Backup of the project file that is performed on the background with no noticeable effect on computer speed as a full database backup of all projects takes too long to execute and slow down computer, also restoring database restore all. Once in a while a full backup using any backup utility [or your software] shall be performed.

I use autosave every 5 minutes, look for backup options in your software.

Photobucket

Member for

16 years 7 months

1) Open initial project

2) Go to Project > Assign baselines, and ensure your updated project is NOT selected as a project or user baseline

3) Go to Project > Maintain baselines, select the updated project, and click "restore".

It should now appear back in your EPS

 

NB: In the future, I advise to take a copy of any project you plan to use as a baseline, so that the original version remains in your EPS.

 

Cheers,

 

G