Suretrak Activity Delay Problem

Member for

13 years 8 months

whether activity B has any other constraints? or any other predecessors?

or this period betn sep-27th n Oct10th is non worknig period?

 

chcek those possibilities!

Member for

24 years 4 months

In a nutshell, the data date is basically the last date that a project is updated.  Until a project is updated, the data date would equal the start date.  All activity start and finish dates prior to the data date are actual dates, while all activities that occur after the data date are calculated by the software (or scheduler). If an activity is in progress during an update you have to consider more than the original duration. You have the actual duration, and then the remaining duration (the duration before, and the duration after the data date).

 

It is good you are asking about the data date because I have seen a lot of people try to use SureTrak and get goofed up, and in every case it was because they didn’t have a good understanding of the data date.

Member for

21 years 8 months

What is the schedule data date?

Member for

19 years 10 months

Hi Ryan

I would suggest that you check your calendars.

Particularly if you have resources on different calendars..

Or maybe you have a constraint on Activity B.

Best regards

Mike Testro

Member for

22 years 10 months

Ryan,

 You have out-of-sequence progress with Activity A.  Activity B’s start is being delayed in order to first complete unfinished work in activities logically proceeding Activity A.  The ‘solution’ is to revise the logic or just be able to explain that Activity B is waiting on Activity C to complete first.  Good luck!