Weighted %age for each activity

Member for

14 years 5 months

SM,

I did costumized my templates by exporting the baseline schedule model to an excel from P6, resources (cost or labor units) assigned in each activity. Using mathematical calculation, its makes easy to  get  the % age or weighted percentage in each activity or in other subgroup. Another thing, as long as you have a baseline plan now, you can make upadate your plan in P6 periodically (monthly or weekly) showing the column of schedule % complete.  

 